Setting up the new interior
Same as for the roof, I want light and bright surfaces
The walls are a bit skewed as well as bent outwards, the corner is somewhat 92°.
Gap will be adjuste with track saw for the countertops, for both directions.
Wanted to start by checking that CAD matches reality, started with prebuilding three cabinets to leans agains the walls
Where possible, blue protective film is left in place untill all is done.
-20241017

Just testing fitment, feet first.
The first impression is positive, it will be easily accesible and airy.

Big window is great for lighting.
-20241019
Mounted the first wall mount, checked level.
allowed for 9cm, bottom of cabinet to floor.
Extremely clear walls are not squared up.

Clearance for waterworks is ok.
-20241020
Measurements and cutouts for drain was done.
Built the top corner cabinet to testfit microwave oven

Somewhat hard to reach controls.
-20241023
Preparation for wire routing was done in several areas.
the top corner cabinet drilled with anglrd hole.
First row of panel.
Tube routed from back of cabinet.
Used a string wrapped around the tube, pulled it through
while lifting the cabinet in place.
-20241024
Time for drying cabinet.
The setup is typical for finnish style, cups and pplates etc. will be dried inside the cabinet, not the countertop.
Will definetly help with keeping clutter away.

Perfectly sized for 600mm cabinet.
Need to omit lowest part of cabinet to allow for ventilation,
On top, a vent is needed, want to keep dust out, så an overlapping mocdel was chosen
-20241027
To get the level correct-ish, modifications and custom made standoffs had to be made for all cabinets.
-20241029
A testmount of up to date build of cabinets.
The tiny inbetweeners can be bult now.

Time to add small cabinets.
-20241031
Three smaller cabinets to fill the gaps were built but these
can not be mounted on the wall rails, they need to be directly
screwed into the side cabinets.
Aligning with quick clamps

The refrigerator sidewall can be added.
-20241103
Adding the oven and the oven drawer showed clearance issues with electrical outlets.
Time to call the electrician.
Besides clashing connectors, side cover panels were test mounted.

Side panels and doors mounted.
Time to leave the house for the winter. no more can be done for this year.
Snow storms are approaching.
-20250421
Back from a snowy winter, water heater cabinet is built
A supporting plate is added to the wall secured by several screws.
-20250426
Connected all tubes and hoses, tigthened all joints and mounted the cabinet to the sidewall and rail.

So far as possible, pipes tightened.
An assortment of wood pieces were cut to be used below countertop.

Stove front, check.
-20250427
Added some panels and doors. cleaned the entire workplace for the next stage.
Counter tops can now be cut and installed
-20250511
A lesson learned, adding bumpstops to cabinets was not so
useful in the long run.
The backwards leaning if all surfaces that I tried to save with wood pieces was not remotely the correct way to adjust the countertops.
I suspected the lower bumpstops and perhaps the awkward, outward bending of the window wall caused a lot of issues.
All has to be removed, bumpstops deleted and height/distance to wall for the
window wall rail needed, also some level adjustements
has to be done.
bumpstops deleted, need to see if anything needs to be used as substitution.
The rail can be offset bfrom the wall with wooden pieces.

First corner wall cabinet adjustment.
It is all now level without wooden standoffs, now it is hanging on the rails but only supported by the front feet on the cabinets.
Perhaps need to create wooden
wedges.
Additionally, A new toy has been picked up
Unboxing
Perhaps now it is time for countertops.
-20250517
Helpful worktable built using simple components was prepared in the
yard.
Firstly, saw need to be mated to rail.
Secondly, the first cut.
Board cut to size, there was no need to angle the cut closest to corner.
Sink placed to bench, placed upside down on masking tape.
Measurments were stated in documentation, heed taken to tubing and pipes underneath and also the faucet installation depth.

Upside down sink.

Masking tape marked, inside outline.
Stove countertop cut to size. no angled cut to compensate for warped walls.
instead hoping that
kitchen tiling will hide it.

Induction stovetop marked.

Marking is clear for sink.

Marking is clear for stovetop.
Time for plungecutting, corners drilled only for Induction stovetop
(following instructions).

Plunge saw with chip guard.

Inside of marking is cut
Cut and saw.

Be careful lifting the weakened wood
![]()
testfit ok.
-20250524
The two pieces are joined with TEC-7, using the clamps and the wood from the corner cabinet to level the surfaces.
![]()
Glue and clamps ready.

Pressure on and screws to drill

Needed ballast for the inner ones

Secured and glued.
-20250525
Faucet can now be dropped into place and threaded with tools that were
in the same packaging.
Before that copper pipe is cut to length (water works)

Depthcheck for faucet.

Bitumen padds attached.
Time's up for today, adding putty to tubes in a few days.
-20250531
Water tubes connected, hoses in place.
time to pressuretest.
(water works)

Time to build som shelves.
-20250607
Used the plunge saw to make cuts that helps the side panels align with the floor.
The house is old, all floors lean into center of the room.

adding the side cover.

Finishing piece made from two parts
-20250622
Took a lot of time just to build som shelves and add som doors

Marking the cabinet doors and shelves.
-20250629
Softstarted the kitchen, had a few people over for an evening of BBQ.
One issue presented itself with the drying shelves being in the wrong order.
While rearranging them, I opted to finilize the water protection and the edge strips.
Moved the holes 85mm downwards for the top level
bottom is ok.

Shelves are in the wrong order.
TEC-7 and platic strips to be added.
First, two pieces need to be cut to length.
Simple trick to get the right lengths is using masking tape.

Masking tape with glue outwards.

Streching the strip over tape.

Masking tape shows where to cut.

Thoroughly massage in the glue

thoroughly press and roll the strips.
Added the shelves and now it is time to let the glue cure.
-20250707
Nothing special, just added a grille to refrigerator top vent.
-20250810
Started the induction stove for the first time, the warning label should have been a bit more clear that the smell of burnt electronics would be that strong.
Removed it from the countertop and ran it full blast outdoors.
This also made it clear that running the oven at the same time was very bad due to very limited ventilation.
approx 10mm clearance, the oven gets very hot.
Added som trash bin rails, nice feature.
Ordered a new setup with blind front and lowering of the oven some 10cm.
Will have to update the
installation at later date.
Currently it is not recommended running the induction stove and oven at the same time.
-20250815
Removed induction stove with oven in place, the bad clearence is visible, barely 1cm for air circulation.
Assembled the lower drawing to get the height for the oven, the space seems to work with a few millimeters to spare.
The stove needs air from its own inlet, cutting the back panel.
Adding a divider that will be pushed all the way back to prevent heated air from the oven to creep up towards the fans.
This new gap allows for the cable to be dropped down the back
of the cabinet.
The divider is IKEA nyttig, it is mounted on slides, adding a piece to the end of it to extend it bit.
leaving a gap in front, hopefully this will push som air below the divider as well as out from the gap in front under the counter.

Nyttig 102.432.96
Started the oven and cooked some water on the stove.
No smell of heated parts nor electronics.
there was a gentle breeze leaving the front of the countertop.
Going to test it again, now it is time to close for the day.
TBC
-20250816